Present a plan to a client

Pro planAnyone who can manage the project's members

A Gantt chart is a working tool, and a client reading one has to learn it first. Present this plan turns the project’s read-only link into an execution plan a client can read: each top-level task is a section, a field you choose becomes the contract column, milestones are diamonds, and dates can be counted in weeks from a milestone such as the contract award.

Present this plan is on the Professional, Business, Enterprise and Enterprise+ plans. On a lower plan the command shows with a lock, and the dialog offers the trial.

  1. Open the project’s Gantt tab, then select Share in the toolbar.

  2. Select Present this plan, below Share a read-only link. If the project has no link yet, the dialog asks you to make one first.

  3. Choose a Contract column: a text, dropdown or number task field, or an outline level (“WBS level 2”, for example), or No contract column. Its values become a filter on the page, and it is the only field added to the shared copy.

  4. Choose where to Count weeks from: a milestone, whose week becomes week 0, or Calendar dates, no anchor to show dates only.

  5. Optionally enter a Version label, for example “Rev B, issued for tender”.

  6. Select Save and present, then Open the presented page to see what the client sees.

The command is shown to people who can share the project: organization admins and people whose project role lets them manage the project’s members. A link straight to the dialog is /projects/<project id>?view=gantt&present=1.

The page opens at the same link, with no account needed:

  • A header with “Execution plan”, the plan’s name, the version label, the date it was saved, who shared it and, with an anchor, which milestone is week 0.
  • One section per top-level task, with the tasks under it indented by level.
  • The columns Task, the contract column, Weeks or Dates, and a timeline. Milestones are amber diamonds, and the other rows are bars.
  • A filter on the contract column, so a client can see only their scope.
  • With a milestone anchor, a Weeks and Dates switch. Weeks read, for example, “Weeks 3 to 7”.
  • Print or save as PDF, which opens the browser’s print dialog.

The page holds what the read-only link holds: task names, dates, and the names of the people assigned and collaborating, with your organization’s name. Task descriptions, costs, currency, custom fields and email addresses are left out. The contract column is the one field added, and an email address in its values is cut at the @.

  • Stop presenting in the dialog returns the link to the plain chart.
  • To end access altogether, turn the link off in the Share dialog’s list of live links. Links last 30 days.

If the workspace moves below the Professional plan, the page stops presenting and the link shows the plain chart.

Which fields can be the contract column? Text, dropdown and number task fields, and the outline levels. Fields that could carry personal or money data (email, phone, URL, currency, long text, date and checkbox fields) are not offered.

Does the client see changes I make after presenting? No. The page is a copy taken when you save. Select Save and refresh to update it.

Can the page be exported as a PDF? Yes, through Print or save as PDF, which uses the browser’s print dialog.