Read the network diagram

All plansAnyone who can see the project; editing links needs Manage task dependencies

The network diagram draws a project the way Microsoft Project’s Network Diagram does: each task is a box, each dependency an arrow between boxes, and the critical path is red. Where the Gantt answers “when”, the diagram answers “what waits on what”, which is the quickest way to check a plan’s logic before you trust its dates.

In Onplana, “PERT” also names the three-point duration estimate used by schedule risk. This view is the network diagram. For a quick chart without an account, see the free PERT chart tool.

  1. Open the project and select the Tasks tab.

  2. Open the menu on the Gantt view button and select Network diagram, after Gantt, Task sheet, Resource sheet and Resource usage. The button then reads Network diagram.

A project's Network diagram fitted to the window: undo and redo, zoom at 62%, Fit to window and Group by summary at the top, then seven task boxes in a chain, each with its early and late dates, duration, float, progress and the person assigned, linked by arrows labelled with their type and lag. The two critical boxes, a regression pass with -1d float and go-live with 0d float, are outlined in red, with a red arrow between them.

The view’s address is /projects/<project id>?view=gantt&subtab=network, so you can share a link that opens it. It is on every plan.

On a phone the view asks for a wider screen; open the plan on a tablet or a computer.

Each task box has its ID and name as its title, then two rows:

Row Left Middle Right
First Early start Duration Early finish
Second Late start Float Late finish

Under them, a bar shows the percent complete and the names of the people assigned. An empty value reads “None”. The dates are the task’s saved dates.

The boxes differ the way Microsoft Project draws them:

  • Critical tasks have a red border and header, and a red float. The legend names it Critical path.
  • Milestones are hexagons with the name, one date and the word “Milestone”.
  • Done tasks (100%) are crossed through with an X; tasks in progress carry one diagonal stroke.
  • When you select a task, the boxes off its path dim, so the chain it sits on stands out.
  • Zoom out, the zoom percentage and Zoom in at the top of the view, and Fit to window to see the whole diagram.
  • Group by summary groups the boxes under their summary tasks.
  • On a large plan, an Overview minimap shows where you are.
  • The arrow keys move from box to box along the links. Double-click a box, or press Enter, to open the task in its form.

The diagram draws up to 20,000 tasks; past that it says so and the Gantt still shows every task. Links that form a loop are drawn dashed, and links to tasks in other projects are not drawn; a line under the diagram counts both.

People who can manage the project’s dependencies (the Manage task dependencies permission) can edit links in the diagram, on a project that is not archived. Everyone else reads it.

Add a link

  1. Drag from the dot on a box to another box.

  2. In the dialog titled with the two task names, choose the Link type: FS (finish-to-start, the default), SS, FF or SF.

  3. Optionally enter a Lag in working days or hours, such as 5d or 4h. A lead is negative: -5d.

  4. Select Add the link.

A link that would make a loop is refused, and the dialog says why; nothing changes.

Remove a link: select the arrow and press Delete (Backspace on a Mac), or select Remove link. Onplana asks first: “Remove this link?”, with the task that will no longer wait and a note that the schedule moves to match.

An arrow that comes from a link on a summary task cannot be removed here. Remove that link on the summary task, in the Gantt or the task form.

Undo and Redo buttons sit beside the view, and Ctrl+Z (Cmd+Z on a Mac) and Ctrl+Y work too. They share the Gantt tab’s undo list, so a link added in the diagram can be undone from the Gantt.

Onplana Schedule, the free desktop app, has the same view: View > Network diagram. While it is on, the View menu adds Critical path, Task path and Fit to window. Links are edited the same way, with undo, unless the plan is read-only, and the diagram exports as PNG or PDF. See Install Onplana Schedule.

Do the dates in the boxes reschedule the plan? No. The boxes show each task’s saved dates. To move tasks to the dates their links allow, use Schedule > Recalculate now on the Gantt.

Why don’t I see the dots on the boxes? You do not have the Manage task dependencies permission on this project, or the project is archived.