October 2026
Finish a project: completion checks, closeout and archive
Section titled “Finish a project: completion checks, closeout and archive”Every project now has a Closeout tab for the end of its life.
- Completion checks are your organization’s definition of done. Some Onplana reads from the project’s data, and a person ticks the rest. They stay off until an Owner or Admin opens Organization Settings → Configuration → Completion readiness, picks a starter set, and chooses whether open checks only warn or stop a project from being completed. Blocking needs Enterprise or Enterprise+.
- Closeout records how a completed or cancelled project ended: a final baseline with its earned value, a closeout report in Project Documents, lessons learned, and a sign-off by the project owner, or by a named panel of reviewers on Enterprise and Enterprise+.
- Archive puts a finished project away. It becomes read-only for everyone and leaves the project lists until it is unarchived; the Archived view on the Projects page finds it.
- ChatGPT and Claude can run the checks, start a closeout, sign it off and archive a project through the Onplana connector.
Complete, close out and archive a project
Do more from any project, task or issue
Section titled “Do more from any project, task or issue”The menus on a project, a task and most other items now end in a Do more block with the next things people reach for:
- Copy link, and Ask AI about this, which opens the assistant with a question about the item for you to review and send.
- Create new: file an issue from a task, or create a task or raise a change request from an issue, each linked back to where it started.
- Log time on this task opens your timesheet with the task and this week filled in, and Link to a goal ties a task to a key result.
- On a project: Import into this project…, Report on this, Automate, Share or export, Collect requests into this project…, Recently deleted (the Recycle Bin kept to that project), and Manage project for its administration.
- Connected here, on a task, a document, a List and the project Overview, shows the other direction: the workflows that fire there, the forms that create work there and the reports that include it.
- On the Projects page, Select acts on several projects at once, and each card shows what the project has attached.
Act on several projects at once
Tasks have collaborators
Section titled “Tasks have collaborators”A task keeps one assignee, the person accountable for it, and can now have up to 20 collaborators: the other people working on it. They can find the task, hear about it and work on it, and the assignee stays its owner.
- My Work shows the tasks you collaborate on, each with a Collaborating chip naming who holds it, and a Role filter separates them from the tasks assigned to you. On the List view, the Mine toggle shows both.
- Collaborators work on the task as their project role allows: change its status, progress and dates, comment, and attach files. Reassigning, moving and deleting it stay with the people who could do those before.
- They are notified when they are added and when someone comments.
- Add them from the task itself, under Collaborators, or under More options while creating one. A +N beside the assignee on the List, Board, Sprint, Backlog and Gantt views shows who else is on a task. Work with task collaborators
- ChatGPT and Claude can manage them too. Ask the agent to add or remove collaborators by name, or to name them as it creates tasks or a whole plan.
- Imports keep everyone on the task. From a Microsoft Project file, one resource becomes the assignee and the others become collaborators when they are in your workspace; anyone not in it yet is added when they accept an invitation. Planner and Project for the web imports do the same with their assignees. Import a Microsoft Project file
The Onplana Tasks desktop app, browser extension and Android app show collaborators too, as does Onplana Projects for SharePoint, and Onplana Schedule can mark a person on a task as collaborating.
Every name opens what it names
Section titled “Every name opens what it names”- Project, client, person and task names are links throughout the app.
- A person has a page: the open tasks they hold and work on, their projects and teams, and their week. A team has its own page too.
- Notifications, activity and audit rows, restored items, report rows and dashboard widgets open the thing they describe.
- The task form opens its parent, sprint, dependencies and project, and its Related section lists what is linked to it.
- Search finds issues, ideas, proposals, clients, deals and more, and Ctrl+K finds items and offers every create action.
Undo an import, or copy a project
Section titled “Undo an import, or copy a project”- Undo import: for 24 hours, the person who ran an import can take it back, from the Import wizard or the import’s row in the history. An import that created a project sends that project to the Recycle Bin; one that added to an existing project removes exactly what it added. Members it added and invitations it sent stay.
- Make a copy in a project’s menu starts the same plan again: tasks at every level with their links, epics, sprints, milestones and tags, and the people too while Bring the people stays ticked. Every task goes back to To do, and comments, files, risks, issues, baselines and time stay behind.
- A SharePoint list of projects imports as a portfolio, one project per row, and a Project XML file’s sprints become the project’s sprints.
Import a SharePoint project list
Paid plans include AI tokens every month
Section titled “Paid plans include AI tokens every month”Professional, Business and Enterprise now include AI tokens every month, per billable seat: 1 million on Professional, 1.5 million on Business and 2.5 million on Enterprise. The allowance resets each calendar month, and unused tokens do not roll over. The Billing tab shows this month’s allowance.
Free keeps its one-time 100,000-token bonus, and Enterprise+ stays unlimited. Prepaid AI credit works as before: buy from $5, it lasts 90 days, and it is spent before the monthly allowance. Understand your AI token budget
Starter is off sale, and Free can try Professional for 14 days
Section titled “Starter is off sale, and Free can try Professional for 14 days”The Starter plan is no longer offered. A workspace already on it keeps its plan and can move up at any time. A Free workspace can instead try Professional for 14 days, once, with no card; it returns to Free by itself and keeps everything made during the trial. The offer now also appears at the project limit: in the New Project dialog, and as a link the ChatGPT or Claude connector can pass on when a chat runs into the limit. It also appears when a Free workspace reaches its member limit, and on the locked project templates. Try Professional for 14 days
Turn on Onplana Services from Billing
Section titled “Turn on Onplana Services from Billing”The Owner of an existing workspace can now add Onplana Services (clients, pipeline, margin) from Organization Settings → Billing, without starting a new workspace. Projects and people stay where they are. Turn on Onplana Services
Verifying your email accepts your invitations
Section titled “Verifying your email accepts your invitations”Someone who signs up with a password at an invited address, without the invitation link, now joins as soon as they verify that address. Every invitation waiting for it, for a workspace or a project, is accepted at the role the inviter chose, and the verification page names what they joined. Verifying your email accepts the invitation
The Gantt: menus, filters, and a look before you leap
Section titled “The Gantt: menus, filters, and a look before you leap”- A two-row toolbar. The title row holds the task count, the timescale, zoom and full screen. The toolbar row keeps the everyday buttons and moves the rest into four menus: View, Schedule, AI and Share. Active filters show as chips under it. Find your way around the toolbar
- Filter by more than the assignee. Status, priority, several people, tags, epic, sprint, a date window, milestones, the critical path, overdue work and your own tasks, remembered per project. Filter the chart
- What if… on a task row previews a slip or a new date: what moves, where the finish lands and who becomes overallocated. Apply saves the one edit, with Undo; Discard writes nothing. Try a change before you make it
- Why the finish date moved. When an edit moves the project finish, the note after it says by how many working days, and Why shows which change did it and the chain of tasks that carried it. See why the finish date moved
- Schedule quality flags on the row. A task the DCMA checks flag carries a small flag by its name, with the findings on hover. Hide flags is in View > Display. See the flags on the Gantt
Baselines are easier to find and to read
Section titled “Baselines are easier to find and to read”- View > Baseline on the Gantt toolbar turns on Show baseline changes: a +3d or -2d chip on each task that moved, and a Baseline finish line. On a project with no baseline it says so, and offers Capture baseline now to the project’s owner and managers.
- The Baselines tab writes a plain summary above the comparison: how far the finish moved and the chain of tasks driving it, how the scope and planned cost changed, and the five largest moves. It uses no AI, and the cost lines show only to people who can see the project’s cost.
- On a phone, the Gantt shows the name column beside the timeline; tap a bar for its card.
Schedule Quality finds dates that break their links
Section titled “Schedule Quality finds dates that break their links”The Gantt draws each task’s saved dates, so a plan can look sound while its links say some tasks should start later. A fifth structure check on the Schedule Quality view, Dates that break their links, counts the open tasks whose saved start is earlier than their dependencies allow and lists the five furthest out. Recalculate on the Gantt moves them. Onplana Schedule has the same check in its Schedule quality drawer, where Plan > Reschedule now moves them. Dates that break their links
Workflow conditions check what they say
Section titled “Workflow conditions check what they say”- A trigger condition the engine cannot read no longer fires. Before, it was skipped and the workflow fired on every event of its kind.
- Empty is one value. For equals and not equals, a blank value, a cleared field and Unassigned (no assignee) are the same.
- Due date passed carries the task’s real status and a separate
Overdue field. A condition on status
OVERDUEnow matches nothing; test Overdue equals true instead. - Timesheet submitted carries the week’s total hours, offered in the builder as Hours submitted for the week.
- Four shipped templates were corrected. An older copy of Auto-Process Timesheets keeps testing progress until you change its step to the week’s hours, and an older Overdue Task Follow-Up keeps escalating without the new Still open? check. Auto-Assign New Tasks and SLA Breach Alert work as described once condition steps read from the task, a server setting that is off by default. Approving a whole week from a workflow is not supported yet.
Onplana Schedule 0.2 unlocks the Project ribbon’s paid commands
Section titled “Onplana Schedule 0.2 unlocks the Project ribbon’s paid commands”Onplana Schedule reached version 0.2 on 15 October. Signed in to a Professional organization or above, it unlocks Plan > Set baseline…, Plan > Move project…, Plan > Links between projects…, Plan > Subproject… and Plan > Manage sprints…. On Business and above, Plan > Schedule risk… runs the plan many times on your computer and gives the P50, P80 and P90 finish, the chance of a date and the tasks that move it. Opening, editing, saving and Schedule quality stay free. Unlock the paid features of Onplana Schedule
This month’s releases also brought:
- the app in Spanish, French, German, Italian, Brazilian Portuguese, Japanese, Simplified Chinese and Arabic, besides English;
- New schedule for a blank plan, and adding and deleting resources on the Resource sheet itself;
- Add to Onplana Tasks, which hands a saved plan to the Tasks app;
- chart PDFs that print Polish, Greek, Cyrillic, Arabic, Chinese, Japanese and Korean text.
Onplana Schedule shows each resource’s work by month
Section titled “Onplana Schedule shows each resource’s work by month”Onplana Schedule, the free desktop app that opens Microsoft Project files, gained a Resource usage view with version 0.1.27 on 30 September: every resource’s work and actual work by month, week or day, the assignments behind that work beneath it, totals for each line and each period, an asterisk on any number that includes flat-estimated work, and File > Export > Resource usage as CSV…. Type actual work for a period on an assignment’s line, and the hours land on the working days it spans. Open Microsoft Project files with Onplana Schedule
The weeks before brought Plan > Compare with another version…, which draws an earlier save or a colleague’s copy as each bar’s baseline and lists every change; Plan > Schedule quality, the DCMA 14-point assessment run on your own computer; and Chart as PDF or picture…, which repeats the ID and task name on every page.
In the browser, the online MPP viewer shows the Resource usage view read-only, fills the screen with the plan on request, and carries an Edit in Onplana Schedule button to the download page.
The direct downloads update themselves. The Microsoft Store and Mac App Store builds carry these with their next update.
Onplana Tasks works without an account, in nine languages
Section titled “Onplana Tasks works without an account, in nine languages”This month’s releases of the Onplana Tasks desktop app, browser extension and Android app brought:
- Use without an account: keep a task list on the device, with nothing sent anywhere, and move it into Onplana when you sign in.
- The apps in Spanish, French, German, Italian, Brazilian Portuguese, Japanese, Simplified Chinese and Arabic, besides English, reading right to left in Arabic.
- Open a schedule file: a Microsoft Project .mpp, .mpx or XML file, a Primavera .xer, a CSV or an Excel file, whose tasks join your list, or, signed in, open the web import to make a project of it.
- Invite people to a project, give a task to someone who has not joined yet, and start a new project in Onplana. On the desktop, a project also opens in Onplana Schedule.
Use Onplana Tasks without an account
Onplana Projects puts your project on its SharePoint site
Section titled “Onplana Projects puts your project on its SharePoint site”Onplana Projects, the SharePoint package, gives a project site a full Onplana page: the project’s tasks with their collaborators, milestones, timeline, issues, risks, ideas, documents, members, approvals and your timesheet, all worked on in place. Six web parts show live Onplana data on any page, a file in a document library can be linked to a task or start one, and someone without access can ask to join your workspace from the site. Your IT team can request the package from support@onplana.com. Use Onplana in SharePoint
Also this month
Section titled “Also this month”- Leave that puts a schedule at risk is flagged. When approved time off overlaps tasks on the critical path or with little float, the project’s owner, managers and time-off approvers get one notification naming the tasks and what it does to the finish. When leave puts a schedule at risk
- Onplana Tasks for Mac is on the Mac App Store, beside the download that updates itself. Install Onplana Tasks for Mac
- Advanced AI moves to Professional. AI risk detection, portfolio insights, Suggest schedule and the levelling insight are now on Professional, so the Professional trial includes them. Compare plans
- Approve documents with a workflow. A new document or version can start a sign-off that locks that version until it is decided, and records who approved which version. On Business. Approve documents with a workflow
- Automate from any item’s menu. Automate on a project, task, folder, document or List opens the workflow builder with the trigger already set. Automate from an item’s menu
- Attach a plan to the AI assistant. The paperclip reads a CSV or Excel plan, answers questions about it and imports it, with Undo for 24 hours. Attach a plan file
- Risks you write yourself. Add risk and Edit risk on a project’s Risks tab, with no AI analysis needed. Keep a risk register
- Tags on the Board and the List. Filter both by tag, and group the List by tag. Tag and filter work
- Export to Excel downloads a project’s task table as you see it. Export the task table to Excel
- Lists. Add the standard lists creates the success factors, assumptions, constraints, stakeholders and decision log lists in one click, and rows paste into a List straight from a spreadsheet. Paste rows into a List
- SharePoint and OneDrive file links, and Microsoft To Do sync, are included from Professional, no longer only from Business. Attach files from SharePoint
- Reports shows in the sidebar for Members.
- Workflows. New workflow opens on a start screen where describing the workflow picks its trigger, and a workflow the AI drafted starts paused until a person turns it on.
- Taking back an AI change. When the assistant changes a dependency, a constraint, a calendar or a baseline, it says how to undo the change or restore the schedule to the moment before.