Start a risk register from a template

All plansMember

Risk Register is a built-in project template for a team that wants a risk register without starting from an empty page. It creates a project whose Risks tab already lists twelve risks most projects meet, a short plan for reviewing them together, and an Assumptions list, so the register and the A of a RAID log are in place on day one. It is available on every plan, Free included.

  • One project, starting the day you create it and running for about five days.

  • One phase, Set up the register, with four tasks, all To Do and unassigned:

    Task When Estimate Priority
    Hold a risk workshop with the team Day 1 4 hours High
    Score each risk: probability and impact Day 2 4 hours High
    Agree a response and an owner for each risk Days 3 and 4 6 hours Medium
    Book a register review every two weeks Day 5 1 hour Medium
  • One milestone, Register agreed, at the end of the five days.

  • Twelve risks on the project’s risk register, listed below.

  • An Assumptions list on the project’s Lists tab, with the columns Assumption, Category, Owner, Validate By, Status and Impact If Wrong, and two rows marked Example: to replace.

Each risk arrives open, with a severity, a category and a recommendation (what would reduce it). Ten of them also carry a probability and an impact in working days; two leave those for your team to set.

Risk Severity Category Probability × impact
A key supplier delivers late High External 40% × 10 days
Requirements change after sign-off High Scope 50% × 8 days
A specialist leaves or is moved to another project High Resource 25% × 12 days
The estimates for the build are too optimistic Medium Schedule 45% × 6 days
Costs rise above the approved budget High Budget Not set
Approvers are not available for reviews when the plan needs them Medium Schedule 35% × 5 days
Connecting to an existing system takes longer than planned High Schedule 30% × 10 days
The test environment is not ready when testing starts Medium Resource 30% × 4 days
People do not take up the new process or system Medium Scope Not set
A security or compliance review raises findings late High External 20% × 8 days
Equipment is damaged in transit Low External 10% × 6 days
The data in the old system is incomplete or wrong Medium Scope 40% × 5 days

They are a starting list, not your list. The first task in the plan, the workshop, is where you remove the ones that do not apply and add the ones that are missing.

  1. From the sidebar, open Projects and select New Project.
  2. Type a name for the project. Choosing a template does not fill the name in.
  3. In the Template picker, under Built-in templates, choose Risk Register. The dialog previews it before anything is created: how many tasks and milestones it has, about how many days it runs, its phase, and “Starts with 12 risks already flagged”.
  4. Select Create Project. The project opens.

The project counts toward your plan’s project limit like any other. You need permission to create projects in your organization, the same as for a blank project.

The page at onplana.com/templates/risk-register offers the same twelve risks as an Excel workbook (.xlsx) to download, with Assumptions, Issues and Dependencies sheets beside the register. Its Open the template free link brings the template into Onplana:

  • If you sign up from it, the first setup screen shows The template you picked with Create the project from this template. Nothing is created until you select it, and Choose something else drops it.
  • If you already have an account and sign in from it, the New Project dialog opens with Risk Register already chosen, and you still select Create Project yourself.

The choice is kept in that browser for a day, so it survives a sign-in with Google, Microsoft or Apple, or a confirmation email opened later the same day.

Work through the four tasks in order:

  1. Workshop. Open Analytics > Risks with the team. Dismiss the risks that do not apply (choose Not relevant as the reason) and use Add risk for the ones that are missing.
  2. Score. Select Owner and review on each card and set Probability (%) and Impact (working days). The two risks without them show “Not set” until you do.
  3. Respond and own. In the same panel, pick an Owner from the project’s members and a Response: Avoid, Mitigate, Transfer or Accept. Template risks start with “No owner” and “Not decided”.
  4. Review. Set a Next review date on each risk. Once it has passed, the risk shows under Risks to review on its owner’s My Work.

Every field and action is described in Keep a risk register.

The template’s risks have no affected tasks, because the project they belong to is yours to plan. A schedule risk run includes a risk only when it has a probability, an impact and at least one affected task, so pick the tasks each risk would delay in its Edit form first.

Open the Lists tab, then Assumptions, and replace the two example rows. If you downloaded the workbook from the template page, its Assumptions sheet has the same columns, so you can add its rows to this list. See Import a spreadsheet into a list.

Is it plan-gated? No. Every plan, Free included, can create a project from a built-in template, and the risk register itself works on every plan.

What language are the risks in? Yours. The project’s name, phase, tasks, milestone and risks are written in the language you chose under Settings. The Assumptions list is created in English, like the other standard lists, and you can rename its columns.

Can I add these risks to a project I already have? Not from the template: it always creates a new project. Add risks to an existing project with Add risk on its Risks tab.

Is it in Onplana Schedule? No. The template is mostly its risks and its list, and a Microsoft Project file has no risk register, so it is not in Onplana Schedule’s template set.